Offshore wind power in the United Kingdom
The United Kingdom became the world leader of offshore wind power generation in October 2008 when it overtook Denmark.[1]
Government direction in the development of offshore wind power advanced in 2016 with the development of strategies and systems.
The total offshore wind power capacity installed in the United Kingdom at the start of 2022 was 11.3 GW. By 2023, the United Kingdom had over 11,000 wind turbines with a total installed capacity of 30 gigawatts (GW): 15 GW onshore and 15 GW offshore,[2]
The UK has set a target to have 50GW of offshore wind capacity by 2030.[3]
History
[edit]The United Kingdom has been estimated to have over a third of Europe's total offshore wind resource, which is equivalent to three times the electricity needs of the nation at current rates of electricity consumption[4] (In 2010 peak winter demand was 59.3 GW,[5] in summer it drops to about 45 GW).
One estimate calculates that wind turbines in one third of United Kingdom waters shallower than 25 metres (82 ft) would, on average, generate 40 GW; turbines in one third of the waters between 25 metres (82 ft) and 50 metres (164 ft) depth would on average generate a further 80 GW, i.e. 120 GW in total.[6] An estimate of the theoretical maximum potential of the United Kingdom's offshore wind resource in all waters to 700 metres (2,300 ft) depth gives the average power as 2200 GW.[7]
The first developments in United Kingdom offshore wind power came about through the now discontinued Non-Fossil Fuel Obligation (NFFO), leading to two wind farms, Blyth Offshore and Gunfleet sands.[8] The NFFO was introduced as part of the Electricity Act 1989 and obliged United Kingdom electricity supply companies to secure specified amounts of electricity from non-fossil sources,[9] which provided the initial spur for the commercial development of renewable energy in the United Kingdom.
Offshore wind projects completed in 2010–2011 had a levelised cost of electricity of £136/MWh, which fell to £131/MWh for projects completed in 2012–14 and £121/MWh for projects approved in 2012–2014; the industry hopes to get the cost down to £100/MWh for projects approved in 2020.[10]
The construction price for offshore windfarms has fallen by almost a third since 2012 while technology improved and developers think a new generation of even larger turbines will enable yet more future cost reductions.[11] In 2017 the UK built 53% of the 3.15 GW European offshore wind farm capacity.[12] In 2020, Boris Johnson pledged that, by the end of the decade, offshore wind would generate enough energy to power every UK home.[13]
In 2013, the 175-turbine London Array wind farm, located off the Kent coast, became the largest offshore wind farm in the world; this was surpassed in 2018 by the Walney 3 Extension.
In 2013 the Offshore Energy Strategic Environmental Assessment (SEA) was first published and has been updated regularly. It is the guiding document from the UK government on offshore energy.[14]
In 2016 the government created the Low Carbon Contracts Company as the party low carbon developers will contract with in the Contracts for Difference (CfD) scheme, the developers having won bids in government auctions. The developers would be paid a flat, index linked rate, for electricity for 15 years. Each contract would have a strike price being the price for electricity reflecting the cost of investing in that specific technology with the developer paid the difference between the strike price and the average market price for electricity.[15]
At the start of 2022 there was a total of 11.26 GW of installed offshore wind capacity.[16] During 2022 an additional 3.2 GW of capacity was added with the commissioning of the Moray East, Triton Knoll and Hornsea Project Two wind farms.[17][18][19] A further 13.6 GW of capacity is either under construction (Neart Na Gaoithe, Sofia, Seagreen & Doggerbank A) or has been awarded a Contract for Difference in Round 3[20] or Round 4.[21]
Offshore wind bidding rounds
[edit]In 1998, the British Wind Energy Association (now RenewableUK) began discussions with the government to draw up formal procedures for negotiating with the Crown Estate, the owner of almost all the United Kingdom coastline out to a distance of 12 nautical miles (22.2 km), to build offshore wind farms. The result was a set of guidelines published in 1999, to build "development" farms designed to give developers a chance to gain technical and environmental experience. The projects were limited to 10 km2 (3.9 square miles) in size and with a maximum of 30 turbines. Locations were chosen by potential developers and a large number of applications were submitted.
Seventeen of the applications were granted permission to proceed in April 2001, in what has become known as Round 1 of United Kingdom offshore wind development.[22]
In 2020, the Boris Johnson-led government decided to permit onshore wind power, and since December 2021 onshore wind developers have been able to compete in subsidy auctions with solar power and offshore wind.[23]
Round 1
[edit]
The first of the Round 1 projects was North Hoyle Wind Farm, completed in December 2003. The final project, Teesside, was completed in August 2013. Twelve Round 1 farms in total are in operation providing a maximum power generating capacity of 1.2 GW. Five sites were withdrawn, including the Shell Flat site off the coast of Lancashire.[24]
Round 2
[edit]Lessons learnt from Round 1, particularly the difficulty in getting planning consent for offshore wind farms, together with the increasing pressure to reduce CO2 emissions, prompted the then Department of Trade and Industry (DTI) to develop a strategic framework for the offshore wind industry. This identified three restricted areas for larger scale development, Liverpool Bay, the Thames Estuary and the area beyond the Wash, called the Greater Wash, in the North Sea. Development was prevented in an exclusion zone between 8 and 13 km offshore to reduce visual impact and avoid shallow feeding grounds for sea birds. The new areas were tendered to prospective developers in a competitive bid process known as Round 2. The results were announced in December 2003 with 15 projects awarded with a combined power generating capacity of 7.2 GW. By far the largest of these is the 900 MW Triton Knoll.[26] As before a full Environmental Impact Assessment (EIA) would be needed along with an application for planning consent.
The first of the Round 2 projects was Gunfleet Sands II, completed in April 2010 and six others are now operational including the London Array, formerly the largest wind farm in the world. Four other Round 2 sites are currently under construction.[24]
Round 1 and 2 Extensions
[edit]In May 2010, the Crown Estate gave approval for seven Round 1 and 2 sites to be extended creating an additional 2 GW of offshore wind capacity.[27] Each wind farm extension required a complete new planning application including an Environmental Impact Assessment and full consultation. The sites are:[28]
- Burbo Bank and Walney: DONG Energy UK.
- Kentish Flats and Thanet: Vattenfall.
- Greater Gabbard: SSE Renewables and RWE Npower Renewables.
- Race Bank: Centrica Renewable Energy.
- Dudgeon: Statoil and Statkraft.
Round 3
[edit]Following on from the Offshore wind SEA announced by the Government in December 2007, the Crown Estate launched a third round of site allocations in June 2008. It followed the success of Rounds 1 and 2, from which important lessons were learnt; Round 3 was on a much bigger scale than the combined total of its predecessors (Rounds 1 and 2 allocated 8 GW of sites, while Round 3 alone could identify up to 25 GW).
The Crown Estate proposed nine offshore zones, within which a number of individual wind farms would be situated. It ran a competitive tender process to award leases to consortia of potential developers. The bidding closed in March 2009 with over 40 applications from companies and consortia and multiple tenders for each zone. The successful bidders were announced on 8 January 2010.
Following the allocation of zones, individual planning applications still had to be sought by developers. The first zone came on stream in 2018; several more have still to be completed, and some have been abandoned (see below).
Round 3 consortia
[edit]During the bidding process there was considerable speculation over which companies had bid for the zones. The Crown Estate did not make the list public and most of the consortia also remained silent. The successful bidders for each zone were eventually announced as follows:[29]
Zone[30] | Zone name | Wind farm site names | Potential power (GW) |
Developer | Notes |
---|---|---|---|---|---|
1 | Moray Firth | Beatrice | 1.3 (0.58) | Moray Offshore Renewables Ltd | Formed from EDP Renováveis and SeaEnergy Renewables Ltd (SERL) Project scaled down to 588 MW Commenced commercial operation in 2018 |
2 | Firth of Forth | Alpha/Bravo | 3.5 | Seagreen Wind Energy Ltd | Partnership between SSE Renewables and Fluor Ltd. SSE withdrawing support beyond the consent process. |
3 | Dogger Bank | Crekye A/B & Teesside A/B/C/D | 7.2 | Forewind Ltd | A consortium made up of SSE Renewables, RWE npower, Statkraft and Statoil. SSE withdrawing support beyond the consent process. Project scaled down to 4.8 GW in 2015 Expected to commence commercial operation in 2024 |
4 | Hornsea | Hornsea One, Two, Three and Four (formerly Heron/Njord/Breesea/Optimus & SPC5/6/7/8) | 6 | Ørsted (formerly SMart Wind Ltd) | SMart Wind was a joint venture between Mainstream Renewable Power and Siemens Project Ventures. 100% acquired in 2015 by DONG Energy, which rebranded as Ørsted in 2017.
Hornsea One (1.2 GW) became fully operational in December 2019.[31] Hornsea Two (1.32 GW) became fully operational on 31 August 2022. Development consent for Hornsea Three (2.4 GW) was granted on 31 December 2020 and Ørsted signed the CfD for the project on 3 August 2022.[32] Hornsea Four remains in development. |
5 | East Anglia | East Anglia ONE/TWO/THREE/ONE NORTH | 7.2 | East Anglia Offshore Wind Limited | Joint venture between ScottishPower Renewables and Vattenfall AB ONE commenced commercial operations in 2020. TWO is expected to be fully operational by 2022. THREE is expected to start construction in 2022 |
6 | Southern Array | Rampion | 0.6 (0.4) | E.ON Climate & Renewables / UK Southern Array Ltd | Located south of Shoreham-by-Sea and Worthing in the English Channel Commenced commercial operation in 2018 |
7 | West of Isle of Wight | Navitus Bay | 0.9 | Eneco Round 3 Development Ltd | West of the Isle of Wight; partnership between Eneco and EDF. Planning permission refused by government in September 2015 due to visual impact.[33] |
8 | Atlantic Array | Atlantic Array | Channel Energy Ltd (Innogy) | Withdrawn in November 2013 as "project uneconomic at current time"[34] | |
9 | Irish Sea | Celtic Array | Celtic Array Limited | Withdrawn in July 2014 due to "challenging ground conditions that make the project economically unviable".[35] | |
Total | 26.7 |
In 2009, during the Round 3 initial proposal stage 26.7 GW of potential capacity was planned. However, due to government planning permission refusal, challenging ground conditions and project financing issues, a number of proposed sites were withdrawn. A number of other sites were also reduced in scope.
Contracts for Difference Allocation Round 1
[edit]Announced in 2014 with winners notified in February 2015, Contracts for Difference (CfD) Allocation Round 1 raised 1.1 GW of offshore wind development in two locations, East Anglia 1 (EA 1) and Neart na Gaoithe. The strike prices were £114.39 and £119.89.[36]
Contracts for Difference Allocation Round 2
[edit]Announced in 2017, the winners of Allocation Round 2 had three offshore wind developments giving 3.2 GW of energy, Triton Knoll, Hornsea 2 and Moray Offshore. the strike price was £74.75 and £57.50.[37]
Contracts for Difference Allocation Round 3
[edit]Called by the Government Contracts for Difference (CfD) Allocation Round 3 was announced in 2019 and represented the first large scale new leasing round in a decade. This offers the opportunity for up to 7 GW of new offshore capacity to be developed in the waters around England and Wales.[38] This is split into four bidding areas, Dogger Bank, Eastern Regions, South East and Northern Wales and Irish Sea.
Five commercial winners that would give a total capacity of 5.46 GW by 2024/25 at a strike price of £39 to £41 MWh were announced later in the year. Three at Doggerbank, Sofia Offshore Wind Farm Phase 1 and Seagreen Phase 1.[39]
Contracts for Difference Allocation Round 4
[edit]Announced in 2021, the CfD Allocation Round 4 results, which included winners for all types of renewable energy, were announced in July 2022 with 6.99 GW by 2026/27 and included Inch Cape Phase 1, EA3 Phase 1, Norfolk Boreas Phase 1, Hornsea Project Three and Moray West Offshore all at a strike price of £37.35.[40]
Contracts for Difference Allocation Round 5
[edit]Announced in 2022, the CfD Allocation Round 5 results announced in 2023 did not have any offshore wind, as the potential bidders did not believe the government had taken inflation and supply chain problems sufficiently into account.[41]
Contracts for Difference Allocation Round 6
[edit]A consultation was announced in late 2023 with comments requested by January 2024, with plans for a CfD Allocation Round 6 being announced in March 2024.[42]
Future plans
[edit]The UK has accelerated its decommissioning of coal power stations aiming for a 2024 phase-out date,[43] and recent British nuclear power stations have encountered significant technical issues and project overruns that have resulted in significant increases in project costs.[44] These issues have resulted in new UK nuclear projects failing to secure project financing. Similarly, SMR technology is not currently economically competitive with offshore wind in the UK. Following the Fukushima nuclear disaster public support for new nuclear has fallen.[45] In response, the UK government increased its previous commitment for 40 GW of Offshore wind capacity by 2030.[46] As of 2020, this represents a 355% increase over current capacity in 10 years. It is expected the Crown Estate will announce multiple new leasing Rounds and increases to existing bidding areas throughout the 2020–2030 period to achieve the government's aim of 40 GW.
Scottish offshore
[edit]In addition to the 25 GW scoped under the Round 3 SEA, the Scottish Government and the Crown Estate also called for bids on potential sites within Scottish territorial waters. These were originally considered as too deep to provide viable sites, but 17 companies submitted tenders and the Crown Estate initially signed exclusivity agreements with 9 companies for 6 GW worth of sites. Following publication of the Scottish Government's sectoral marine plan for offshore wind energy in Scottish territorial waters in March 2010,[47] six sites were given approval subject to securing detailed consent. Subsequently, 4 sites have been granted agreements for lease.[48]
In 2022 Crown Estate announced the outcome of its application process for ScotWind Leasing, the first Scottish offshore wind leasing round in over a decade and the first ever since the management of offshore wind rights were devolved to Scotland. 17 projects were selected with a capacity of 25 GW.
List of newly operational and proposed offshore wind farms
[edit]Farm | Commissioned | Estimated completion |
Power (MW) | No. Turbines | Operator | Notes | Round |
---|---|---|---|---|---|---|---|
Race Bank | February 2018[51] | 573 | 91 | Ørsted and Macquarie Group | Consent granted July 2012[52] | 2 | |
Aberdeen Bay (EOWDC) | September 2018[53] | 92 | 11 | Vattenfall | Demonstration site for new turbines. Consent granted March 2013.[54] Project under construction. Use of 8 MW turbines planned utilising the Vestas "short tower" option. | Demo | |
Kincardine (Phase 1) | October 2018 | 2 | 1 | Kincardine Offshore Wind | Consent granted March 2017[55][56][57][58] Commercial scale demonstration of a floating wind farm.[59][60] | Demo | |
Rampion | November 2018[61] | 400 | 116 | RWE, Green Investment Bank, Enbridge | Construction began in January 2016.[2] First electricity delivered to the grid in November 2017.[62] RWE (50.1%) Green Investment Bank (25%) Enbridge (24.9%)[63] | 3 | |
Beatrice | July 2019[64] | 588 | 84 | SSE plc, Copenhagen Infrastructure Partners and Red Rock Power LTD | Offshore pile construction has started.[65] Eligible for government CfD. First power generated in July 2018.[66] Fully operational in June 2019[67] Uses Siemens Gamesa 7 MW turbines. | STW. | |
Hornsea Project One | January 2020[68] | 1218 | 174 | Ørsted, Global Infrastructure Partners | Offshore construction began in January 2018.[69] First power in March 2019.[70] Eligible for government CfD. Use of Siemens Gamesa 7 MW turbines.[70] | 3 | |
East Anglia ONE | July 2020[71] | 714 | 102 | Vattenfall and Scottish Power Renewables | Consent granted June 2014.[72][73] Uses Siemens Gamesa 7 MW turbines. Turbine installation was completed in April 2020.[74] | 3 | |
Kincardine (Phase 2) | August 2021[75] | 48 | 5 | Kincardine Offshore Wind | Consent granted March 2017[55] First turbine towed into place in August 2018 and first power generated in October 2018.[56][57][58] Commercial scale demonstration of a floating wind farm.[59][60] | Demo | |
Moray East | April 2022[76] | 950 | 100 | EDP Renewables, Engie, Diamond Green, China Three Gorges | Consent granted March 2014.[77] Use of Vestas 9.5MW turbines planned. First turbine installed January 2021.[78] EDP Renewables (33.3%), Engie (23.3%), Diamond Green Limited (33.4%) and China Three Gorges (10%)[79] | 3 | |
Triton Knoll | April 2022[19] | 855 | 90 | RWE, J-Power, Kansai Electric Power | Consent granted July 2013[80] Uses Vestas 9.5MW turbines. All foundations completed in August 2020, first power in March 2021.[81][82] RWE (59%), J-Power (24%) and Kansai Electric Power (16%)[18] | 2 | |
Hornsea Project Two | August 2022[83] | 1386 | 165 | Ørsted | Consent granted August 2016 for phase 2 (Breesea & Optimus Wind – 900MW each).[84] Use of Siemens Gamesa 8.4MW turbines. First power in December 2021.[85] | 3 | |
Seagreen (Phase 1) | October 2023[86] | 1140 | 114 | SSE and Total | Consent granted October 2014 for phase 1 (Alpha & Bravo – 525MW each)[17] Successful in the spring 2019 capacity auction.[20] The project is projected to grow to 1,500 MW after phase 1. Vestas 10 MW turbines to be used.[87] First foundation laid October 2021.[88] First power in August 2022.[89] | 3 | |
Dogger Bank A | 2024[20][90][91] | 1235 | 95 | SSE, Equinor, Eni | Consent granted February 2015 for phase 1 (Creyke Beck A & B – 1235MW each)[92] Successful in the spring 2019 capacity auction.[20] The wind farm will use 95 of the GE Haliade-X 13 MW.[93] Equinor (40%), SSE Renewables (40%) and Eni (20%).[94] First foundation laid in July 2022.[95] First power transmitted 10 October 2023[96] | ||
Neart Na Gaoithe | 2024[97] | 448 | 54 | EDF Renewables, ESB | Consent granted October 2014.[17] Use of Siemens Gamesa 8MW turbines planned. Construction began in August 2020.[98] EDF (50%) and ESB (50%).[99] Delayed until 2024. | STW | |
Moray West | Early 2025[100] | 882[101] | 60[101] | EDP Renewables, ENGIE[101] | Consent granted June 2019.[102] Partially successful ln CFD Round 4 for 294 MW of the project[103] Offshore construction started early October 2023[104] | ||
Dogger Bank B | 2024–25[20] | 1235 | 95 | SSE, Equinor, Eni | Consent granted February 2015 for phase 1 (Creyke Beck A & B – 1235MW each)[92] Successful in the spring 2019 capacity auction.[20] The wind farm will use 95 of the GE Haliade-X 13 MW.[93] Equinor (40%), SSE Renewables (40%) and Eni (20%).[94] | 3 | |
Dogger Bank C | 2024–25 (Phase 1),[20][105] revised completion 2026 | 1218 | 87 | SSE and Equinor | Formerly known as Teesside A. Consent granted August 2015.[106] Successful in the spring 2019 capacity auction.[20] The wind farm is planning to use the Haliade-X 14 MW from GE, the world's largest wind turbine.[107] | 3 | |
East Anglia THREE | 2026–27[103] | 1372[103] | 100 | Scottish Power Renewables, Vattenfall and OPR | Consent granted August 2017.[108] Successful ln CFD Round 4[103] Construction started July 2022.[109] | 3 | |
Sofia | 2023–24 (Phase 1),[20] revised completion 2026 | 1400 | 100 | RWE | Consent granted August 2015.[106] Formerly known as Dogger Bank Teesside B. Successful in the spring 2019 capacity auction.[20] Use of Siemens Gamesa 14 MW turbines planned. | 3 | |
Hornsea Project Three | 2026–27[103] | 2852[103] | 231 | Ørsted | Consent granted in 2020.[110] Final investment decision confirmed December 2023[111] Successful in CFD Round 4[103] | 3 | |
ForthWind Offshore Wind Demonstration Project | 2023–24[20] | 12 | 2 | Cierco | Consent granted December 2016.[112] | ||
Inch Cape | 2026–27[103] | 1080[103] | 72 | Red Rock Power and ESB | Consent granted October 2014.[17] RSPB Judicial Review overturned.[113] Project downsized to 784 MW following issues raised during consultations. New application in August 2018 with fewer but taller turbines.[114] Successful in CFD Round 4[103] | STW | |
Dounreay Trì | 2026[115] | 10 | 2 | Hexicon AB and Dounreay Tri | Consent granted March 2017.[116] Has since been put on hold[117] | ||
Hornsea Project Four | 2027 | 180 | Ørsted | Anticipated development consent order is expected to be submitted in 2020.[118] The wind farm is expected to start construction in 2023, and operation at 2027 at the earliest[119] The project's capacity is unknown by Orsted due to the ever increasing size of available wind turbines to the project. | |||
Norfolk Vanguard | Mid 2020s | 1800 | 90–180 | Vattenfall | A development consent order was given for the project in June 2020.[120] The project aims to install all of the offshore cabling for the Vanguard location as well as the sister wind farm, Boreas which is located adjacent to the project.[121] | 3 | |
Norfolk Boreas (Phase 1) | 2026–27[103] | 1396[103] | unknown | Vattenfall, now RWE | Consent Granted December 2021. Successful in CFD Round 4.[103] Development was suspended in July 2023 due to rising costs.[122] Development was purchased by RWE and is expected to resume.[123] | ||
Dogger Bank D | 1320 | unknown | SSE and Equinor | Initial surveys started in mid-August and are expected to run until the end of November 2022[124] | |||
Dogger Bank South | 3000 | unknown | RWE | Go ahead to enter lease agreement with Crown Estate July 2022.[125] Survey work complete October 2022.[126] | 4 | ||
Seagreen 1A | 500[127] | 36[127] | SSE and Total | Consent from Scottish Government to increase the capacity of this phase from 360 MW to 500 MW October 2022[127] | |||
Rampion 2 | 2026 | 1200[128] | 90[129] | RWE | RWE is aiming to submit final proposals to the Planning Inspectorate in 2023[129] | ||
North Falls | 2030 | 504[130] | up to 72[130] | RWE | Secured Agreements for Lease with the Crown Estate in 2020[131] | ||
Sheringham Shoal Wind Farm Extension | 719[132] | up to 56[132] | Equinor | Application for Sheringham Shoal Wind Farm Extension submitted[133] | |||
Dudgeon Wind Farm Extension | Shared with Sheringham Shoal | Shared with Sheringham Shoal | Equinor | Application for Dudgeon Offshore Wind Farm Extension submitted[133] | |||
Awel y Môr | 2030[134] | estimated 500 | up to 50[135] | RWE | DCO granted September 2023.[136] Application for Marine License submitted. |
References
[edit]- ^ Jha, Alok (21 October 2008). "UK overtakes Denmark as world's biggest offshore wind generator". The Guardian. London. Retrieved 12 November 2008.
- ^ a b "UK Wind Energy Database (UKWED)". RenewableUK. Retrieved 23 October 2023.
- ^ "Offshore wind". Retrieved 14 November 2023.
- ^ Oswald, James; Raine, Mike; Ashraf-Ball, Hezlin (June 2008). "Will British weather provide reliable electricity?" (PDF). Energy Policy. 36 (8): 2312–2325. doi:10.1016/j.enpol.2008.04.033.
- ^ National Grid Table of Indicative Triad Demand Information showing 7 January 2010 peak Archived 18 January 2013 at archive.today. Bmreports.com.
- ^ MacKay, David. Sustainable Energy – without the hot air. pp. 60–62. Retrieved 3 April 2010.
- ^ "Two Terawatts average power output: the UK offshore wind resource". Retrieved 2 August 2010.
- ^ RenewableUK – Offshore Wind Introduction Archived 29 July 2012 at archive.today. Bwea.com.
- ^ REPP report into Non-Fossil Fuel subsidies in the UK Archived 25 September 2017 at the Wayback Machine. Repp.org (30 June 1998).
- ^ "Cost Reduction Monitoring Framework". ORE Catapult. February 2015. pp. 7 and. Archived from the original (pdf) on 22 July 2015. Retrieved 20 July 2015.
- ^ Huge boost for renewables as offshore windfarm costs fall to record low The Guardian
- ^ UK built half of Europe's offshore wind power in 2017 The Guardian
- ^ Ziady, Hanna (6 October 2020). "All 30 million British homes could be powered by offshore wind in 2030". CNN. Retrieved 6 October 2020.
- ^ "Offshore Energy Strategic Environmental Assessment (SEA): An overview of the SEA process". Retrieved 14 November 2023.
- ^ "Contracts for Difference". 9 November 2016.
- ^ "Table 6.1. Renewable electricity capacity and generation". GOV.UK. 31 March 2022. Retrieved 3 April 2022.
- ^ a b c d ScottishGovernment. "ScottishGovernment – News – Consent for offshore wind development". scotland.gov.uk. Archived from the original on 18 June 2015. Retrieved 9 June 2015.
- ^ a b "About Triton Knoll – Triton Knoll". Retrieved 8 July 2021.
- ^ a b Ltd, Renews (8 August 2022). "Triton Knoll owners request OFTO handover exemption". reNEWS - Renewable Energy News.
- ^ a b c d e f g h i j k "Contracts for Difference (CfD) Allocation Round 3: results - published 20 September 2019, revised 11 October 2019". GOV.UK. Retrieved 14 October 2022.
- ^ "Contracts for Difference (CfD) Allocation Round 4: results (accessible webpage)". GOV.UK. Retrieved 14 October 2022.
- ^ "The Crown Estate map of Operational Offshore energy – Round 1 wind farms in red" (PDF). Retrieved 3 February 2018.
- ^ Ambrose, Jillian (16 March 2020). "Planning applications for UK clean energy projects hit new high". The Guardian. Retrieved 16 March 2020.
- ^ a b "The Crown Estate – Our portfolio". The Crown Estate. Archived from the original on 24 April 2014. Retrieved 9 June 2015.
- ^ Walker, Shell (29 January 2016). "Collett News: UK's Largest Turbine Blades to Muirhall Wind Farm – Collett Transport". collett.co.uk. Retrieved 27 March 2019.
- ^ "The Crown Estate map of Operational Offshore energy – Round 2 wind farms in pink" (PDF). Retrieved 3 February 2018.
- ^ "The Crown Estate R1 & R2 extensions announcement". Archived from the original on 24 August 2010.
- ^ "Map of R1 & R2 wind farm extensions, The Crown Estate" (PDF). Archived from the original (PDF) on 15 June 2011.
- ^ "Round 3 developers, The Crown Estate". Thecrownestate.co.uk. Archived from the original on 2 February 2012. Retrieved 3 January 2012.
- ^ "Map of R3 Zones, The Crown Estate" (PDF). Retrieved 3 February 2018.
- ^ "World's Largest Offshore Wind Farm Fully Up and Running". OffshoreWIND.biz. 30 January 2020. Retrieved 3 December 2022.
- ^ "National Infrastructure Planning: Hornsea Project Three Offshore Wind Farm". Planning Inspectorate. 31 December 2020. Retrieved 3 December 2022.
- ^ Macalister, Terry (11 September 2015). "Tories reject Navitus Bay offshore windfarm". The Guardian. Retrieved 20 November 2015.
- ^ "RWE Innogy – Press release 09 July 2013 Export cables in at Gwynt y Môr Offshore Wind Farm". rwe.com. Archived from the original on 10 May 2015. Retrieved 9 June 2015.
- ^ "Centrica Celtic Array Project website". Archived from the original on 29 April 2014. Retrieved 3 February 2018.
- ^ "Contracts for Difference (CFD) Allocation Round One Outcome" (PDF). 26 February 2015.
- ^ "Contracts for Difference Second Allocation Round Results" (PDF). 11 September 2017.
- ^ "Offshore Wind Leasing Round 4 | The Crown Estate". www.thecrownestate.co.uk. Retrieved 20 February 2020.
- ^ "Contracts for Difference (CfD) Allocation Round 3: results - published 20 September 2019, revised 11 October 2019". 11 October 2019.
- ^ "Contracts for Difference Allocation Round 4 results" (PDF). 7 July 2022.
- ^ "Offshore Wind Developers Take a Pass on UK's Fifth CfD Round as Maximum Bid Price Was Too Low". 8 September 2023.
- ^ "Open consultation Contracts for Difference: contract changes for Allocation Round 6". 19 December 2023.
- ^ Vaughan, Adam (4 February 2020). "UK coal phase-out date pulled forward". Business Green. ISSN 0261-3077. Retrieved 25 February 2020.
- ^ Vaughan, Adam (10 April 2018). "EDF warns of delays at Flamanville nuclear power station in France". The Guardian. ISSN 0261-3077. Retrieved 20 February 2020.
- ^ Vaughan, Adam (4 August 2015). "Public support for UK nuclear and shale gas falls to new low". The Guardian. ISSN 0261-3077. Retrieved 20 February 2020.
- ^ "Queen's Speech: Government ramps up offshore wind target to 40GW". businessgreen.com. 19 December 2019. Retrieved 20 February 2020.
- ^ – Scottish Government Blue Seas – Green Energy Report Archived 24 January 2012 at the Wayback Machine. Scotland.gov.uk (18 March 2011).
- ^ Table of Scottish Offshore Zones, The Crown Estate Archived 9 November 2014 at the Wayback Machine. Thecrownestate.co.uk.
- ^ Eccleston, Paul (4 October 2007). "Britain's massive offshore wind power potential". The Daily Telegraph. Archived from the original on 12 January 2022. Retrieved 21 July 2021.
- ^ – UKWED Offshore wind farms Archived 25 June 2014 at the Wayback Machine. renewableuk.com.
- ^ "Race Bank comes alive". 1 February 2018. Retrieved 3 February 2018.
- ^ Offshore Wind News website. Offshorewind.biz (6 July 2012).
- ^ "Cutting-edge Aberdeen offshore wind farm officially opened". 7 September 2018.
- ^ "Consent for Donald Trump row wind farm announced", BBC News, 26 March 2013
- ^ a b "Kincardine Offshore Wind Farm". The Independent. 10 March 2017. Retrieved 24 April 2017.
- ^ a b "First Kincardine Floating Wind Turbine Sets Off". 17 August 2018. Retrieved 25 September 2018.
- ^ a b "Kincardine floating wind project to generate first power next week – News for the Oil and Gas Sector". 7 September 2018. Retrieved 25 September 2018.
- ^ a b "First power at Kincardine floating project". Windpower Offshore. Retrieved 27 March 2019.
- ^ a b "Floating wind turbines planned off Kincardine coast". BBC News. 16 May 2014. Retrieved 10 August 2015.
- ^ a b "Green light for Aberdeen floater". 9 March 2017. Retrieved 14 March 2017.
- ^ "Rampion wind farm officially launched at i360 ceremony". Brighton and Hove Independent. 30 November 2018. Retrieved 3 December 2018.
- ^ "Rampion Offshore Wind Farm". rampionoffshore.com. Retrieved 18 April 2018.
- ^ "Owners | Rampion Offshore Wind | E.ON, Enbridge and GIG |". Rampion Offshore Wind. Retrieved 8 July 2021.
- ^ "Scotland's largest offshore wind farm officially opened". BBC News. 29 July 2019.
- ^ OffshoreWIND.biz website. (24 April 2017).
- ^ "First power exported from Beatrice Offshore Wind Farm". 19 July 2018. Retrieved 27 March 2019.
- ^ "Beatrice Offshore Windfarm Ltd". beatricewind.com.
- ^ "World's Largest Offshore Wind Farm Fully Up and Running". 30 January 2020.
- ^ "Cable success at Hornsea One". Retrieved 31 December 2018.
- ^ a b "The world's biggest offshore wind farm, Hornsea 1, generates first power". orsted.com.
- ^ "East Anglia One Now Officially Fully Operational". 3 July 2020.
- ^ Press Association (17 June 2014). "UK government gives green light to offshore windfarm". The Guardian. Retrieved 9 June 2015.
- ^ "East Anglia One offshore wind farm plan reduced in size". BBC News. 26 February 2015. Retrieved 5 March 2015.
- ^ "Turbine installation complete on East Anglia ONE offshore windfarm". ScottishPower Renewables.
- ^ "Largest Floating Offshore Wind Farm Stands Complete". Offshore Wind. 24 August 2021.
- ^ Garden, Peter. "Notice To Mariners" (PDF). Moray East Offshore Windfarm. Retrieved 26 January 2023.
- ^ "Moray Offshore Renewables – Home". morayoffshorerenewables.com. Archived from the original on 19 May 2015. Retrieved 9 June 2015.
- ^ "Lamprell Gearing to Send Off First Moray East Jackets". 16 January 2020.
- ^ "Moray offshore windfarm, Outer Moray Firth, Scotland". power-technology.com. Retrieved 8 July 2021.
- ^ "Giant Triton Knoll offshore wind farm given green light". businessgreen.com. 11 July 2013. Retrieved 9 June 2015.
- ^ "Triton Knoll Foundations and Export Cables in Place". 26 August 2020.
- ^ "Triton Knoll Offshore Wind Farm generates first power". Triton Knoll. 1 March 2021. Retrieved 7 March 2021.
- ^ "Hornsea 2: North Sea wind farm claims title of world's largest". BBC News. 31 August 2022.
- ^ "Hornsea Offshore Wind Farm (Zone 4) – Project Two". planningportal.gov.uk. Retrieved 18 October 2016.
- ^ "Triton Knoll Foundations and Export Cables in Place". 20 December 2021.
- ^ Seagreen Offshore Wind Farm Fully Up and Running
- ^ "Seagreen jacket foundations arrive at Port of Nigg". Seagreen Wind Energy. 11 August 2021. Retrieved 2 September 2021.
- ^ "Major milestone as first jacket installed". 11 October 2021. Retrieved 14 October 2021.
- ^ "Scotland's biggest offshore wind farm to generate first power - BBC News". 2022-08-23. Archived from the original on 23 August 2022. Retrieved 2023-06-10.
{{cite web}}
: CS1 maint: bot: original URL status unknown (link) - ^ "Government green lights record-breaking Dogger Bank offshore wind farm". businessgreen.com. 17 February 2015. Retrieved 15 June 2015.
- ^ "Dogger Bank Wind Farm Building the world's largest offshore wind farm". sserenewables.com. Retrieved 17 July 2023.
- ^ a b "Dogger Bank Creyke Beck". planningportal.gov.uk. Archived from the original on 26 January 2015. Retrieved 9 June 2015.
- ^ a b "GE Renewable Energy launches the uprated Haliade-X 13 MW wind turbine for the UK's Dogger Bank Wind Farm". GE. General Electric. 21 September 2020. Retrieved 23 September 2020.
- ^ a b "Dogger Bank". equinor.com. Retrieved 8 July 2021.
- ^ "Laying the foundation for net zero". 26 July 2022. Retrieved 26 July 2022.
- ^ "Largest offshore wind farm celebrates power milestone - BBC News". 2023-10-12. Archived from the original on 12 October 2023. Retrieved 2023-10-13.
- ^ "Neart na Gaoithe commissioning delayed to 2024". 28 February 2022. Retrieved 5 January 2023.
- ^ "Neart na Gaoithe project enters first phase of offshore construction". EDF.
- ^ "ESB is taking a 50 percent stake in major Scottish offshore wind farm with EDF Renewables". esb.ie. Archived from the original on 9 July 2021. Retrieved 8 July 2021.
- ^ "Moray West Offshore Wind Farm Project". www.moraywest.com. Retrieved 2023-10-29.
- ^ a b c "Moray West signs contract with Siemens Gamesa :: moraywest". moraywest.com. Retrieved 7 July 2022.
- ^ "Moray West". 4COffshore. Retrieved 10 August 2019.
- ^ a b c d e f g h i j k l m "Contracts for Difference (CfD) Allocation Round 4: results (accessible webpage)". GOV.UK. Retrieved 7 July 2022.
- ^ "Work Planned for the Period 09th October to 15th October 2023" (PDF). 2023-11-04. Retrieved 2023-11-04.
- ^ "Display panels for Dogger Bank Teesside A&B" (PDF). Forewind. 2013. Archived from the original (PDF) on 24 September 2015. Retrieved 15 June 2015.
- ^ a b "Dogger Bank Teesside A&B". planningportal.gov.uk. Archived from the original on 9 May 2015. Retrieved 6 August 2015.
- ^ "GE Renewable Energy finalizes contracts for third phase of Dogger Bank offshore wind farm | GE News". www.ge.com. Retrieved 8 July 2021.
- ^ "National Infrastructure Planning East Anglia THREE Offshore Wind Farm webpage". Offshore Wind. Retrieved 15 November 2017.
- ^ "East Anglia THREE". Retrieved 17 January 2023.
- ^ "Hornsea Project Three Offshore Wind Farm". planning inspectorate. Retrieved 1 January 2021.
- ^ "Ørsted takes final investment decision on Hornsea 3 Offshore Wind Farm". hornseaproject3.co.uk. Retrieved 29 December 2023.
- ^ "ForthWind Offshore Wind Demonstration Project". 4COffshore. Retrieved 21 September 2018.
- ^ "Judge overturns offshore wind farms block". BBC News. 16 May 2017. Retrieved 3 February 2018.
- ^ "No more than 72 turbines off Scottish coast in new Inch Cape design".
- ^ "CIP puts plans for new floating Pentland project forward". 4c Offshore.
- ^ "Dounreay Trì". 4COffshore. Retrieved 21 September 2018.
- ^ "Dounreay Tri – Hexicon". hexicon.eu. Archived from the original on 28 January 2020. Retrieved 21 February 2020.
- ^ "About the project". Orsted. Retrieved 2 June 2020.
- ^ "Hornsea Project Four". Orsted. Retrieved 2 June 2020.
- ^ "Norfolk Vanguard". Retrieved 3 July 2020.
- ^ "Norfolk Boreas Offshore Wind Farm". Retrieved 3 July 2020.
- ^ "Norfolk Boreas: Work on offshore wind farm stops over soaring costs - BBC News". 2023-07-20. Archived from the original on 20 July 2023. Retrieved 2023-07-22.
{{cite web}}
: CS1 maint: bot: original URL status unknown (link) - ^ Buljan, Adrijana (2023-12-22). "RWE Buys Vattenfall's Norfolk Trio for EUR 1.1 Billion, Restarts Paused Norfolk Boreas Project". Offshore Wind. Retrieved 2023-12-29.
- ^ Buljan, Adrijana (6 October 2022). "BREAKING: SSE, Equinor Plan 1.3 GW Dogger Bank D Offshore Wind Project". Offshore Wind. Retrieved 7 October 2022.
- ^ RWE. "Green light for Dogger Bank South projects, as RWE prepares for lease agreements". rwe.com. Retrieved 8 October 2022.
- ^ Memija, Adnan (19 October 2022). "Fugro Wraps Up Surveys for RWE's Dogger Bank South". Offshore Wind. Retrieved 19 October 2022.
- ^ a b c Buljan, Adrijana (12 October 2022). "Half of Seagreen Offshore Wind Turbines Installed". Offshore Wind. Retrieved 13 October 2022.
- ^ "The Project - Rampion 2". 18 November 2020. Retrieved 19 October 2022.
- ^ a b "Rampion 2: Offshore windfarm extension area 'nearly halved'". BBC News. 17 October 2022. Retrieved 19 October 2022.
- ^ a b "Facts & Figures". North Falls Offshore Wind Farm. Retrieved 19 October 2022.
- ^ Memija, Adnan (18 October 2022). "SSE, RWE Gather Public Feedback for North Falls Offshore Wind Farm". Offshore Wind. Retrieved 19 October 2022.
- ^ a b "Sheringham Shoal Extension Project and Dudgeon Extension Project" (PDF).
- ^ a b "Equinor submits application for Sheringham Shoal and Dudgeon Offshore Wind Farm Extensions". equinor.com. 2 September 2022. Retrieved 19 October 2022.
- ^ Designs, Daydream. "Awel y Môr Indicative Timeline". Awel Y Mor. Retrieved 19 October 2022.
- ^ Designs, Daydream. "Awel y Môr Project Details". Awel Y Mor. Retrieved 19 October 2022.
- ^ "National Infrastructure Planning: Awel y Môr Offshore Wind Farm". Retrieved 2023-11-04.
External links
[edit]- COWRIE Collaborative offshore wind research into the environment
- [http://www.4coffshore.com/offshorewind/ 4C Offshore's Wind Farm Map and Database
- The Crown Estate Invests in 25 GW of Offshore Wind Power containing all UK offshore wind farms.]